How to Migrate to the Cloud: Large AWS Migrations in Practice
Use AWS's official method to set migration strategies, plan waves, write rollback plans and build a business case, and avoid tools closed to new customers.
Once you have many servers, you can't schedule a migration ad hoc. Before you start, decide which workloads move first, how fast the migration can finish, and how to roll back if a cutover goes wrong. AWS Prescriptive Guidance breaks a large migration into phases, strategies, waves, and cutover, and it also gives benchmark numbers for building a business case.
This article walks through that guidance and focuses on the rules and numbers you can use directly. In the past year, migration tools have changed: a service stopped accepting new customers, and a product was renamed. The article gives the dates.
Three phases: build the landing zone in the mobilize phase
AWS divides a large migration into three phases that run in sequence1:
- Assess: build the business case for the migration1.
- Mobilize: this is usually when you build the AWS landing zone and run a deeper application portfolio assessment1.
- Migrate and modernize: initialization comes first, then implementation. The guide puts initialization at 1–3 months, which you use to prepare the platform and the people and to write the runbooks1.
Implementation migrates servers in batches, wave by wave. The guide calls this repeatable process a migration factory1. Before the factory starts, the initialization stage reviews the landing zone design and confirms that there is enough bandwidth for the scale of the migration1.
A landing zone is the orchestration framework for a baseline AWS environment. It gives you a starting baseline for multi-account architecture, identity and access management, governance, data security, network design, and logging2. You can build it in two ways: with AWS Control Tower, the AWS managed landing zone service, or as a custom build. The two approaches need different levels of AWS knowledge from the team2. Either way, the output of this step should be a defined, secure landing zone that is ready for migration2.
You also don't have to build the whole landing zone at once. The wave planning guide lists creating or extending the landing zone (accounts, security, networking, infrastructure services, and so on) as routine preparation work inside a wave3. When you schedule the work, you can make sign-off on the basics (account structure, identity and permissions, networking, and logging) a prerequisite for the first wave, then extend the landing zone as later waves need it.
The 7 Rs: refactoring is not recommended for large migrations
A migration strategy is the way you move a workload to AWS. There are seven of them, known as the 7 Rs4. The table below summarizes the official definitions4:
| Strategy | Official definition |
|---|---|
| Retire | Applications to decommission or archive |
| Retain | Applications that stay in the source environment, or that are not ready to migrate yet |
| Rehost | Also called lift and shift: move the application to the cloud without any changes |
| Relocate | Move a large number of servers as a whole from an on-premises platform to the cloud version of the same platform; also used to move between virtual private clouds (VPCs), Regions, or accounts |
| Repurchase | Also called drop and shop: replace the application with a different version or a different product |
| Replatform | Make some optimizations during the migration |
| Refactor | Change the application architecture to take full advantage of cloud-native features |
The guide gives numeric thresholds for deciding whether to retire an application based on utilization. Applications with average CPU and memory utilization below 5% are called zombie applications, and you can consider retiring them. Applications with average CPU and memory utilization between 5% and 20% over 90 days are called idle applications, and you can also pick some of them to retire4. During the inventory, aggregate the utilization data from your discovery tools by application, and you can shortlist these two kinds of candidates first4.
Refactoring is not recommended for large migrations4. Refactoring means changing the application while you migrate it. It is the most complex of the seven strategies, and it becomes hard to control once the number of applications grows4. The guide recommends that you rehost, relocate, or replatform first, and modernize after the migration. In a large migration, use refactor only when no other strategy is feasible4.
The rule-of-thumb numbers for the business case point the same way: typically, about 70% of workloads can be rehosted, relocated, or replatformed, and another 5% can be retired5.
Waves and cutover: start slow, then speed up, and plan the way back first
Wave speed and cadence
Ramp up the migration speed step by step. The guide's example: to migrate 1,000 servers in 6 months, you can start at 5 servers per week and gradually increase to 50–100 servers per week6. The first few waves are usually small because the team is still refining its runbooks. Review and revise the runbooks after every cutover6.
These cadence rules are worth writing into the project plan:
- The guide recommends keeping each wave within 6–10 weeks3. Work that takes longer, such as completely rewriting an application component, is usually better handled outside the waves3.
- The guide recommends that the portfolio workstream, which takes inventory and plans the waves, stay 5 waves ahead of the migration workstream, which migrates and cuts over the servers6. This buffer makes sure the migration team always has servers ready to migrate6.
When you define dependency groups, separate soft dependencies from hard ones. A soft dependency does not depend on where the components are deployed, so the two systems can be migrated separately. A hard dependency depends on location. For example, if an application server and its database depend heavily on low latency, moving only one of them causes functional or performance problems that can't be resolved3. When you analyze communication data, first exclude traffic from shared services such as Active Directory, backup, and monitoring. Otherwise these services tie the whole migration scope together into one group3.
In each wave, after the applications move to AWS, schedule a post-migration support period, for example 3 days. During this period the operations team and the migration team are fully available to resolve issues3.
Cutover approaches and the rollback plan
There are two ways to cut over: switch everything at once, or cut over in phases (canary deployments)7. A phased cutover is more complex and takes more time, but it usually needs less downtime and allows faster rollback. For this reason it is the most common approach for business-critical production workloads7. Development and test environments that can tolerate some downtime are a good fit for an all-at-once cutover7. If an application can't tolerate increased latency between the data source and the application servers, you also have to cut over all at once and move the servers and the database together7.
A rollback plan must spell out three things7:
- Checkpoints during the cutover, and the predefined criteria that trigger a rollback;
- The rollback strategy, including how to handle the data;
- One point of contact, who decides whether to fix forward or roll back.
If no new data has been written when you roll back, restore the on-premises instances and switch traffic back through the load balancer or DNS7. If the application has already created new transactions after a successful cutover, the cloud database is the primary, and the on-premises database is likely stale. In that case, you can use AWS Database Migration Service (AWS DMS) to build a fail-forward database by replicating the data to a new on-premises database. If problems occur, DMS rolls the application back to this designated database instead of the stale old one7. The other two approaches are dual writes, where the application logic writes to both the old and new databases, and native database backup and restore. If you use backup and restore, test how long the restore takes in a non-production environment before the cutover7.
Business case: start with infrastructure, then look at the rest
The job of a directional business case is to reach a credible enough conclusion from the limited data available early on. That conclusion should let the project secure resources to set up a core team and carry out the follow-on assessment5.
Start with an infrastructure cost comparison, and confirm that the result is compelling enough before you go further5. At this stage, look only at a few cost reductions that are easier to assess, such as compute elasticity, buying through Savings Plans, removing zombie servers, and rightsizing compute5. The guide gives the following benchmarks (TCO means total cost of ownership):
| Item | Benchmark | Condition in the guide |
|---|---|---|
| Time to complete | 2–4 weeks | Typically5 |
| Size threshold | Portfolios of more than 400 servers show a positive return from infrastructure cost reduction alone within 3 years on AWS; portfolios of 250 servers within 5 years | Usually; the guide notes this can vary5 |
| Effect of the priority cost reductions | About 30% TCO savings | Typically5 |
| Savings Plans | Up to 75% cost reduction | For production servers and other servers with utilization above 36%5 |
| Operations staffing | About 150 servers per full-time employee on premises, about 400 on AWS | Staffing benchmark5 |
| Business case period | 5 years | Matches the hardware refresh cycle for servers, storage, and network devices, typically5 |
Portfolios below the size threshold may need more detailed analysis before you can reach a conclusion5. When the business case period matches the hardware refresh cycle, the as-is cost of each scenario includes exactly one hardware refresh5.
For operations staffing, apply the 150 and 400 benchmarks to the number of on-premises servers and the number of Amazon EC2 instances, respectively. Work out the hours saved, then convert them to money with the team's blended labor cost rate5.
Tools: check each product's current status first
If you plan from old material, you can easily pick a service that no longer accepts new customers, or search under an old name and miss the new documentation.
- AWS Migration Hub: no longer accepts new customers as of November 7, 20258. If you need similar capabilities, AWS recommends that you explore AWS Transform8. The AWS wave planning guide also says that AWS Transform can help you analyze dependencies and plan waves3.
- AWS Application Migration Service (MGN): renamed AWS Transform MGN9. The rename announcement was published on June 8, 202610. The rehost automation tools that AWS lists now show the new name4. Some documentation still uses the old name. For example, the Migration Hub documentation still says AWS Application Migration Service8. Search for both names when you look things up.
Migration Evaluator is a free managed service from AWS. It can do rightsizing assessments, give purchasing recommendations, and compare software licensing options5. The limitations listed on the page include that it assesses only x86 architecture servers (Windows and Linux) and does not support migration cost modeling5.
The Migration Evaluator page in the AWS migration tools guide also states11:
- The page defines the utilization data used to choose instance sizes as time-series data with a 5-minute sampling interval, collected for at least 1 month. Migration Evaluator can choose sizes based on statistics of CPU and memory utilization over time11.
- TCO for both on premises and AWS is estimated over 1 year and 3 years. Migration cost estimates are not provided11.
This page was last updated on May 15, 202311. The guide recommends a 5-year business case period5, but Migration Evaluator gives only 1-year and 3-year estimates and leaves out migration costs11. You need to fill in these two parts yourself.
Use AWS DMS for database migration. It can do one-time migrations, and it can also replicate changes continuously to keep the source and target databases in sync12. To change database engines, convert the database schema first. You can use the managed DMS Schema Conversion, which is based on the conversion engine of the AWS Schema Conversion Tool (AWS SCT)13. You can also download AWS SCT to your local computer and convert there12. DMS Schema Conversion converts only the schema and does not migrate data. You still move the data with the DMS data migration feature13.
Checklist
- Start with a directional business case, and spend 2–4 weeks comparing infrastructure costs5. For smaller portfolios, allow time for more detailed analysis5.
- Screen applications using the utilization data from your discovery tools: zombie applications with average CPU and memory utilization below 5%, and idle applications between 5% and 20% over 90 days. Assess each one to see whether it can be retired4.
- Assign a 7R strategy to every application. Rely mainly on rehost, relocate, and replatform. Where an application needs refactoring, try to wait until after the migration to change it4.
- Start the first wave only after the landing zone's account structure, identity and permissions, networking, and logging have passed sign-off2.
- Keep each wave within 6–10 weeks3. Start the first few waves small, and always keep the portfolio workstream 5 waves ahead of the migration workstream6.
- In each wave's rollback plan, spell out three things: checkpoints and trigger criteria, the data handling strategy, and the person who makes the call7. For databases that will receive new writes after cutover, prepare a fail-forward database in advance, or test how long backup and restore takes in a non-production environment7.
- Schedule a post-migration support period after cutover, for example 3 days. Review each wave when it ends, and apply the lessons to later waves3.
- AWS Migration Hub has not accepted new customers since November 7, 2025. Evaluate AWS Transform for new migration plans instead8. Change every mention of MGN in internal documents to AWS Transform MGN, and search for both the old and new names when you look things up9.
The information in this article was checked in November 2026. For products and pricing, refer to each vendor's official website.
Sources
The numbers in the text match the sources below; click one to jump here. All sources are official documentation or announcements.
- 1 Phases of a large migration - AWS Prescriptive GuidanceAWS · docs.aws.amazon.com
- 2 Landing zone - AWS Prescriptive GuidanceAWS · docs.aws.amazon.com
- 3 Wave planning - AWS Prescriptive GuidanceAWS · docs.aws.amazon.com
- 4 About the migration strategies - AWS Prescriptive GuidanceAWS · docs.aws.amazon.com
- 5 Creating a directional business case - AWS Prescriptive GuidanceAWS · docs.aws.amazon.com
- 6 Stage 2: Implementing a large migration - AWS Prescriptive GuidanceAWS · docs.aws.amazon.com
- 7 Cutover stage - AWS Prescriptive GuidanceAWS · docs.aws.amazon.com
- 8 What Is AWS Migration Hub? - AWS Migration HubAWS · docs.aws.amazon.com
- 9 General questions - AWS Transform MGNAWS · docs.aws.amazon.com
- 10 AWS Application Migration Service 现已更名为 AWS Transform MGN - AWSAWS · aws.amazon.com
- 11 Migration Evaluator - AWS Prescriptive GuidanceAWS · docs.aws.amazon.com
- 12 What is AWS Database Migration Service? - AWS Database Migration ServiceAWS · docs.aws.amazon.com
- 13 Converting database schemas using DMS Schema Conversion - AWS Database Migration ServiceAWS · docs.aws.amazon.com